
25 Nov 06 - Our Second Work Weekend
We've been waiting for the cement to be
poured which was held up by the poor weather. We decided to go ahead
and do the wall framing and then install the walls once the floor had been
poured. This weekend we had two new mentors who really taught us a lot
about framing and why it's done a certain way. At the end of the day,
we had framed both end walls and the main wall with openings for a door and
a window.
Saturday, 19 May 07
Worked for a day building the wooden floor. Put
in the floor joists, cross-braced them and put chicken wire under the
joists. Then we filled between the joists with insulation and put on
the sub-flooring.

16/17 June 07
A busy weekend but got lots done. We installed
the framing we had previously built and then put up the roof rafters.
Then we nailed on the roofing panels, installed the flashings and put on the
shingles. Still had some panels left, so we closed in the north wall
and installed the window and door and covered that wall with Typar.
23 June 07
Small group of us finished panelling the two end walls.
23 July 07
The young people involved in this project are away for
awhile so I'm updating their page for them. Some are at Cadet Training
Camps and some have gone to Kenya, via England, to build a library for the
Kenyan children. They've taken books with them and it should be a very
good experience for them. Their work on this Libro project will
certainly help them with the construction of the new library. Well
done gang.
Before they left, they managed to get all the siding
and flashing installed and the tile floor laid. They had the help of
two excellent mentors, George and Mike, and did a tremendous job.
They've installed some of the insulation but had to leave some so the
tradesmen could install the wiring and plumbing. One more weekend when
they return and the project will be ready for use.
 |